Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 45% of the total throughput (manufacturing cycle) time is spent on non-value-added activities. Delivery cycle time is 12 hours, waiting time during the production process is 3 hours, queue time prior to starting the production process is 2 hours, and inspection time is 1.2 hours.
-What is the move time recorded for the operation?
A) 1.5 hours
B) 6.5 hours
C) 5.8 hours
D) 0.85 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q83: Hart Manufacturing operates an automated steel fabrication
Q84: Last year a company had stockholder's equity
Q85: Which of the following statements provide(s)an argument
Q86: Ferris Wares is a division of a
Q87: Saffer Corporation keeps careful track of the
Q89: Durkee Corporation keeps careful track of the
Q90: Which of the following three statements are
Q91: The use of return on investment as
Q92: The division's return on investment (ROI)is closest
Q93: Chace Products is a division of a