Solved

During the Most Recent Month at Coggan Corporation,queue Time Was

Question 49

Essay

During the most recent month at Coggan Corporation,queue time was 5.3 days,inspection time was 0.5 day,process time was 1.9 days,wait time was 4.5 days,and move time was 0.5 day.
Required:
a.Compute the throughput time.
b.Compute the manufacturing cycle efficiency (MCE).
c.What percentage of the production time is spent in non-value-added activities?
d.Compute the delivery cycle time.

Correct Answer:

verifed

Verified

a.Throughput time
= Process time + Inspe...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions