Multiple Choice
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of standard direct labor-hours. The following events occurred during March:
• 8,600 pounds of sand were purchased at a cost of $7,310.
• 7,200 pounds of sand were used for core tests.
• 840 actual direct labor-hours were worked at a cost of $8,610.
• Actual variable manufacturing overhead incurred was $3,200.
-The materials price variance for March is:
A) $860 unfavorable
B) $860 favorable
C) $281 unfavorable
D) $281 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Hickory Corporation, which produces commercial safes, has
Q3: Hickory Corporation, which produces commercial safes, has
Q4: Gentile Corporation makes a product with the
Q5: Fabiano Corporation makes a product whose direct
Q6: A materials price variance is favorable if
Q8: Snuggs Corporation makes a product with the
Q9: The standard cost per unit is computed
Q10: Kibodeaux Corporation makes a product with the
Q11: Todco planned to produce 3,000 units of
Q12: The following materials standards have been established