Multiple Choice
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of standard direct labor-hours. The following events occurred during March:
• 8,600 pounds of sand were purchased at a cost of $7,310.
• 7,200 pounds of sand were used for core tests.
• 840 actual direct labor-hours were worked at a cost of $8,610.
• Actual variable manufacturing overhead incurred was $3,200.
-The labor efficiency variance for March is:
A) $480 favorable
B) $480 unfavorable
C) $192 favorable
D) $192 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Todco planned to produce 3,000 units of
Q12: The following materials standards have been established
Q13: Landram Corporation makes a product with the
Q14: Snuggs Corporation makes a product with the
Q15: The following materials standards have been established
Q17: Kibodeaux Corporation makes a product with the
Q18: The Wright Company has a standard costing
Q19: Sande Corporation makes a product with the
Q20: The Richie Company uses a standard costing
Q21: The Geurtz Company uses standard costing. The