Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of standard direct labor-hours. The following events occurred during March:
• 8,600 pounds of sand were purchased at a cost of $7,310.
• 7,200 pounds of sand were used for core tests.
• 840 actual direct labor-hours were worked at a cost of $8,610.
• Actual variable manufacturing overhead incurred was $3,200.
-The variable overhead efficiency variance for March is:
A) $320 unfavorable
B) $320 favorable
C) $360 unfavorable
D) $360 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q43: A manufacturing company that has only one
Q44: Snuggs Corporation makes a product with the
Q45: Kibodeaux Corporation makes a product with the
Q46: The following materials standards have been established
Q47: Imme Corporation's variable overhead is applied on
Q49: The following data have been provided by
Q50: Caquias Corporation makes a product with the
Q51: Jardell Corporation makes a product with the
Q52: Jardell Corporation makes a product with the
Q53: Igel Corporation makes a product with the