Multiple Choice

Roye Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 3,300 tenant-days, but its actual level of activity was 3,330 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for September:

Data used in budgeting:
Roye Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 3,300 tenant-days, but its actual level of activity was 3,330 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for September:  Data used in budgeting:   Actual results for September:   -The overall revenue and spending variance (i.e. ,the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for September would be closest to: A) $3,200 F B) $3,470 F C) $3,200 U D) $3,470 U Actual results for September: Roye Kennel uses tenant-days as its measure of activity; an animal housed in the kennel for one day is counted as one tenant-day. During September, the kennel budgeted for 3,300 tenant-days, but its actual level of activity was 3,330 tenant-days. The kennel has provided the following data concerning the formulas used in its budgeting and its actual results for September:  Data used in budgeting:   Actual results for September:   -The overall revenue and spending variance (i.e. ,the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for September would be closest to: A) $3,200 F B) $3,470 F C) $3,200 U D) $3,470 U
-The overall revenue and spending variance (i.e. ,the variance for net operating income in the revenue and spending variance column on the flexible budget performance report) for September would be closest to:


A) $3,200 F
B) $3,470 F
C) $3,200 U
D) $3,470 U

Correct Answer:

verifed

Verified