Multiple Choice
Capizzi Corporation has an activity-based costing system with three activity cost pools-Machining, Order Filling, and Other. In the first stage allocations, costs in the two overhead accounts, equipment depreciation and supervisory expense, are allocated to three activity cost pools based on resource consumption. Data used in the first stage allocations follow:
Machining costs are assigned to products using machine-hours (MHs) and Order Filling costs are assigned to products using the number of orders. The costs in the Other activity cost pool are not assigned to products. Activity data for the company's two products follow:
-The activity rate for the Order Filling activity cost pool under activity-based costing is closest to:
A) $4.00 per order
B) $1.43 per order
C) $1.00 per order
D) $40.00 per order
Correct Answer:

Verified
Correct Answer:
Verified
Q22: Ollivier Corporation has an activity-based costing system
Q23: Goold Corporation uses activity-based costing to
Q24: Pedroni Corporation uses activity-based costing to compute
Q25: Spendlove Corporation has provided the following data
Q26: Yoke Corporation has provided the following data
Q28: Zee Corporation has provided the following data
Q29: Umanzor Corporation uses activity-based costing to assign
Q30: Dillner Company uses an activity-based costing system
Q31: Dillner Company uses an activity-based costing system
Q32: Brisky Corporation uses activity-based costing to compute