Recent Maintenance Costs of Prideaux Corporation Are Listed Below

Question 19

Multiple Choice

Recent maintenance costs of Prideaux Corporation are listed below: Recent maintenance costs of Prideaux Corporation are listed below:   Management believes that maintenance cost is a mixed cost that depends on machine-hours. -Using the least-squares regression method,the estimate of the variable component of maintenance cost per machine-hour is closest to: A) $9.36 B) $9.49 C) $14.06 D) $9.23 Management believes that maintenance cost is a mixed cost that depends on machine-hours.
-Using the least-squares regression method,the estimate of the variable component of maintenance cost per machine-hour is closest to:


A) $9.36
B) $9.49
C) $14.06
D) $9.23