Solved

Playtime Corporation Assume That Playtime Corp.has Agreed to Construct a New Playground

Question 50

Multiple Choice

Playtime Corporation
Assume that Playtime Corp.has agreed to construct a new playground for Surrey County for $2,450,000.Construction of the new playground will begin on March 17,2012 and is expected to be completed in August 2013.At the signing of the contract Playtime Corp.estimates that it will cost $1,750,000 to build the playground.
-At the end of 2012 Playtime provided the following information about the project: Playtime Corporation Assume that Playtime Corp.has agreed to construct a new playground for Surrey County for $2,450,000.Construction of the new playground will begin on March 17,2012 and is expected to be completed in August 2013.At the signing of the contract Playtime Corp.estimates that it will cost $1,750,000 to build the playground. -At the end of 2012 Playtime provided the following information about the project:   What percentage is the playground complete? A)  62.5% B)  66.7% C)  55.6% D)  50.0% What percentage is the playground complete?


A) 62.5%
B) 66.7%
C) 55.6%
D) 50.0%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge