Multiple Choice
Arrow Industries employs a standard cost system in which direct materials inventory is carried at standard cost.Arrow has established the following standards for the prime costs of one unit of product. During November,Arrow purchased 160,000 pounds of direct materials at a total cost of $304,000.The total factory wages for November were $42,000,90% of which were for direct labor.Arrow manufactured 19,000 units of product during November using 142,500 pounds of direct materials and 5,000 direct labor hours.What is the direct materials price variance for November?
A) $14,250.
B) $14,400.
C) $16,000.
D) $17,100.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2418/.jpg" alt=" What is the
Q10: A favorable materials price variance coupled with
Q11: The following information summarizes the standard cost
Q24: Production cost variances are input variances,while sales
Q29: The production volume variance is the difference
Q30: The production volume variance is computed by
Q67: The sales price variance is the actual
Q98: The intercept of the flexible budget-line is
Q142: In general, the direct labor efficiency variance
Q147: The basic difference between a master budget