Multiple Choice
Sullivan Inc.reports the following information about resources.At the beginning of the year,Sullivan estimated it would spend $180,000 for materials,$42,000 for purchasing,$35,000 for setups,and $36,000 for repairs. Compute unused resource capacity for setups for Sullivan.
A) $2,500.
B) $1,080.
C) $1,500.
D) $1,000.
Correct Answer:

Verified
Correct Answer:
Verified