Lerner Inc Has 6,600 Machine Hours Available Each Month

Question 2

Multiple Choice

Lerner Inc has 6,600 machine hours available each month.The following information on the company's three products is available: Lerner Inc has 6,600 machine hours available each month.The following information on the company's three products is available:   If market demand exceeds the available capacity,in what sequence should orders be filled to maximize the company's profits? A) Product X first,product Z second,and product Y third. B) Product Y first,product Z second,and product X third. C) Product Y first,product X second,and product Z third. D) Product Z first,product X second,and product Y thirD.X CM/hr = 20/2 = $10;Y: 21/3 = $7;Z: 17.50/2 = 8.75 If market demand exceeds the available capacity,in what sequence should orders be filled to maximize the company's profits?


A) Product X first,product Z second,and product Y third.
B) Product Y first,product Z second,and product X third.
C) Product Y first,product X second,and product Z third.
D) Product Z first,product X second,and product Y thirD.X CM/hr = 20/2 = $10;Y: 21/3 = $7;Z: 17.50/2 = 8.75

Correct Answer:

verifed

Verified

Related Questions