Solved

Compute the Correct Variances: Budgeted Sales $110,000: Actual Sales $118,000

Question 46

Multiple Choice

Compute the correct variances: Budgeted sales $110,000: Actual sales $118,000.Actual direct labour $40,000: Budgeted direct labour $42,000.


A) Sales variance $8,000 F: Direct labour variance $2,000 F
B) Sales variance $8,000 F: Direct labour variance $2,000 U
C) Sales variance $8,000 U: Direct labour variance $2,000 F
D) Sales variance $6,000 U: Direct labour variance $4,000 U

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions