Multiple Choice
If projected factory overhead is $150 000 p.a.and projected direct labour hours are 30 000 hours p.a.,the overhead application rate is:
A) $5 per Direct labour Hour
B) $30 per Direct labour Hour
C) 20c per Direct labour Hour
D) $150 000