Multiple Choice
Snappy Company has a job-order cost system and uses a predetermined overhead rate based on direct Labour-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct Labour-hours were estimated at £100,000 and 40,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of £5,000 in direct materials and £2,400 in direct Labour. The Labour rate is £6 per hour. By the end of the year, Snappy had worked a total of 45,000 direct Labour-hours and had incurred £110,250 actual manufacturing overhead cost.
-
If Job #334 contained 200 units, the unit cost on the completed job cost sheet would be:
A) £37.00.
B) £42.00.
C) £41.90.
D) £39.50.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Nil Co. uses a predetermined overhead rate
Q2: Steele Company uses a predetermined overhead
Q3: The three cost categories appearing on a
Q4: Pinnini Co. uses a predetermined overhead rate
Q6: Newcastle Company's beginning and ending inventories
Q7: Malcolm Company uses a predetermined overhead
Q8: The Collins Company uses predetermined overhead
Q9: Newcastle Company's beginning and ending inventories
Q10: The sum of all amounts transferred from
Q11: The Bristol Company uses a job-order