Multiple Choice
The CPM network consists of arcs and nodes. The ______ represent the actual activities while the ______ (events) represent when the activity starts and finishes.
A) nodes / arcs
B) arcs / nodes
Correct Answer:

Verified
Correct Answer:
Verified