Multiple Choice
The Juab Company has a Freight Department that delivers scrap metal from salvage yards to its two fabricating facilities--the Emory Plant and the Salina Plant. Operating data for the two plants for last year follow: Budgeted costs consist of $150,000 fixed costs and $0.50 variable cost for each ton of scrap delivered to the plants. Actual costs incurred in the Freight Department were $52,800 variable, and $165,000 fixed. Juab allocates variable and fixed service department costs separately. The level of budgeted fixed costs is determined by peak-period needs. The Emory Plant requires 40% of the peak-period capacity and the Salina Plant requires 60%.
-How much fixed Freight Department costs should be charged to the Emory Plant at the end of the year for performance evaluation purposes?
A) $60,000
B) $65,625
C) $66,000
D) $56,250
Correct Answer:

Verified
Correct Answer:
Verified
Q31: Warehouse Services is a service department in
Q32: Lindon Hospital has a Food Services Department
Q33: Lindon Hospital has a Food Services Department
Q34: The fixed costs of Baxter Company's personnel
Q35: Fixed costs budgeted for Caldwell Company's
Q37: Wilson Company maintains a cafeteria for its
Q38: Kosek Corporation's Maintenance Department provides services to
Q39: Since service departments do not engage in
Q40: All of a service department's actual costs
Q41: Lump-sum charges for service department fixed costs