Multiple Choice
Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed: During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of standard direct labor-hours. The following events occurred during March:
• 8,600 pounds of sand were purchased at a cost of $7,310.
• 7,200 pounds of sand were used for core tests.
• 840 actual direct labor-hours were worked at a cost of $8,610.
• Actual variable manufacturing overhead incurred was $3,200.
-The labor rate variance for March is:
A) $4,578 unfavorable
B) $1,470 unfavorable
C) $4,578 favorable
D) $1,470 favorable
Correct Answer:

Verified
Correct Answer:
Verified
Q124: Gentile Corporation makes a product with the
Q125: The following data for November have been
Q126: The Litton Company has established standards as
Q127: Hurren Corporation makes a product with the
Q128: The following data have been provided by
Q130: Snuggs Corporation makes a product with the
Q131: The following direct labor standards have been
Q132: A labor efficiency variance resulting from the
Q133: Ideal standards should be used for forecasting
Q134: Mazzo Corporation makes a product with the