Multiple Choice

Job 731 was recently completed.The following data have been recorded on its job cost sheet: Job 731 was recently completed.The following data have been recorded on its job cost sheet:   The company applies manufacturing overhead on the basis of machine-hours.The predetermined overhead rate is $14 per machine-hour.The total cost that would be recorded on the job cost sheet for Job 731 would be: A) $3,288 B) $5,094 C) $4,254 D) $2,418 The company applies manufacturing overhead on the basis of machine-hours.The predetermined overhead rate is $14 per machine-hour.The total cost that would be recorded on the job cost sheet for Job 731 would be:


A) $3,288
B) $5,094
C) $4,254
D) $2,418