Multiple Choice
In a production scheduling LP,the demand requirement constraint for a time period takes the form
A) Beginning inventory + Production + Ending inventory > Demand.
B) Beginning inventory -Production - Ending inventory = Demand.
C) Beginning inventory + Production - Ending inventory = Demand.
D) Beginning inventory - Production - Ending inventory > Demand.
Correct Answer:

Verified
Correct Answer:
Verified