Multiple Choice
To determine how to crash activity times,
A) normal activity costs and costs under maximum crashing must be known.
B) shortest times with crashing must be known.
C) realize that new paths may become critical.
D) All of these are correct.
Correct Answer:

Verified
Correct Answer:
Verified