Essay
Consider a project that has been modeled as follows:
a.Draw the PERT/CPM network for this project and determine the project's expected completion time and its critical path.
b.Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.Can one person perform A,G,and I without delaying the project?
d.By how much can activities G and L be delayed without delaying the entire project?
e.How much would the project be delayed if activity G was delayed by seven hours and activity L was delayed by four hours? Explain.
Correct Answer:

Verified
Correct Answer:
Verified
Q30: Precedence relationships among activities are critical in
Q31: For an activity with more than one
Q32: A senior MIS design class project team
Q33: Use the following network of related activities
Q34: A project network is shown below.Use a
Q36: For an activity with more than one
Q37: The latest finish time for an activity
Q38: The variance in the project completion time
Q39: Activities G,P,and R are the immediate predecessors
Q40: Which of the following is always true