Consider a Project That Has Been Modeled as Follows

Question 35

Essay

Consider a project that has been modeled as follows: Consider a project that has been modeled as follows:   ​  a.Draw the PERT/CPM network for this project and determine the project's expected completion time and its critical path. b.Can activities E and G be performed simultaneously without delaying the minimum project completion time? c.Can one person perform A,G,and I without delaying the project? d.By how much can activities G and L be delayed without delaying the entire project? e.How much would the project be delayed if activity G was delayed by seven hours and activity L was delayed by four hours? Explain. ​
a.Draw the PERT/CPM network for this project and determine the project's expected completion time and its critical path.
b.Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.Can one person perform A,G,and I without delaying the project?
d.By how much can activities G and L be delayed without delaying the entire project?
e.How much would the project be delayed if activity G was delayed by seven hours and activity L was delayed by four hours? Explain.