Essay
Non-Slip Tile Company (NST)has been using production runs of 100,000 tiles,10 times per year to meet the demand of 1,000,000 tiles annually.The setup cost is $5000 per run,and holding cost is estimated at 10% of the manufacturing cost of $1 per tile.The production capacity of the machine is 500,000 tiles per month.The factory is open 365 days per year.
a.What production schedule do you recommend?
b.How much is NST losing annually with its present production schedule?
c.What is the maximum number of tiles in inventory under the current policy? Under the optimal policy?
d.What fraction of time is the machine idle (not producing tiles)under the current policy? Under the optimal policy?
Correct Answer:

Verified
D = 1,000,000,P = 6,000,000,Ch = 0.10,C...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q15: Which of the following would NOT be
Q16: Inventory position is<br>A)the amount of inventory on
Q17: An assumption in the economic production lot
Q18: The terms "inventory on hand" and "inventory
Q19: The EOQ model<br>A)determines only how frequently to
Q21: A firm that is presently using the
Q22: For the production lot size,Q,the average inventory
Q23: As lead time for an item increases,the
Q24: Show the total cost expression and calculate
Q25: If lead time is longer than the