Dilloo Company Uses an Activity-Based Costing System with Three Activity

Question 5

Multiple Choice

Dilloo Company uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system: Dilloo Company uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity based costing system:   The  Other  activity cost pool consists of the costs of idle capacity and organization-sustaining costs. You have been asked to complete the first-stage allocation of costs to the activity cost pools. -How much cost, in total, would be allocated in the first-stage allocation to the Order Size activity cost pool? A)  $271,000 B)  $280,500 C)  $297,000 D)  $264,000 The "Other" activity cost pool consists of the costs of idle capacity and organization-sustaining costs.
You have been asked to complete the first-stage allocation of costs to the activity cost pools.
-How much cost, in total, would be allocated in the first-stage allocation to the Order Size activity cost pool?


A) $271,000
B) $280,500
C) $297,000
D) $264,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions