Multiple Choice
The Lee Company uses a job-order costing system. The following data were recorded for June: Overhead is charged to production at 80% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and 238 have been delivered to customers.
-Lee's Work in Process inventory balance on June 30 was:
A) $4,100
B) $3,940
C) $3,300
D) $9,450
Correct Answer: