In order to aid project team to make a decision of an acquisition, they employ several approaches to gather additional information. The document that solicits a formal proposal from a potential vendor, developer, or service provider is called _________
A) RFI
B) RFQ
C) RFP
D) RFC
E) RFD
Correct Answer: