menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Systems Analysis and Design
  4. Exam
    Exam 2: Project Management
  5. Question
    The Critical Path in a Network Diagram Is the Shortest
Solved

The Critical Path in a Network Diagram Is the Shortest

Question 105

Question 105

True/False

The critical path in a network diagram is the shortest path from the project inception to completion.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q100: The person or group that funds a

Q101: It is not wise to identify tasks

Q102: The _ is a dynamic schedule that

Q103: The feasibility study is performed during project

Q104: A functional lead manages a group of

Q106: Explain PERT analysis.

Q107: Diane needs to create a work plan

Q108: Usually, a functional lead oversees the progress

Q109: Explain the role of the project champion.

Q110: Project management is the second major component

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines