Multiple Choice
A budget adjusted to reflect a budget allowance based on actual activity achieved rather than the planned level of activity in the original budget is a:
A) static budget.
B) rolling budget.
C) controllable budget.
D) flexible budget.
Correct Answer:

Verified
Correct Answer:
Verified