Multiple Choice
Which of the following methodologies might be most appropriate if you have a system project with: clear requirements;very familiar technologies;not all that complex;must be reliable;a somewhat longer schedule and the schedule visibility is not important?
A) Waterfall
B) Parallel
C) Iterative
D) System prototyping
E) V-model
Correct Answer: