Multiple Choice
Which of the following methodologies might be most appropriate if you have a system project with: unclear user requirements;unfamiliar technologies;very complex;must be reliable;a short to medium time schedule and the schedule visibility is somewhat important?
A) Waterfall
B) Parallel
C) Iterative
D) System prototyping
E) Throwaway prototyping
Correct Answer:

Verified
Correct Answer:
Verified