Multiple Choice
Mya is managing a project.Unfortunately,the entire project team lost four days due to a hurricane in the area and a couple of the project team lost even more time when dealing with insurance claims and rebuilding.At the six-week mark of a nine-week project,she figures the team is one week behind.What might be the BEST solution?
A) Add several people to the project to get it back to schedule
B) Do not change the schedule, but expect the project and development teams to work longer days and every-other weekend.
C) Since the project is about 16% behind, increase the project to about 10-and-one-half weeks
D) Since the project is about 20% behind, increase the project to about 12 week.
E) Add three people to the project - AND - increase the overall project by one week (to a total of ten weeks)
Correct Answer:

Verified
Correct Answer:
Verified
Q4: This factor is the number one influence
Q6: PMP is Project Management Professional.
Q8: Extreme Programming (XP)is BEST characterized as:<br>A)A 'Quick
Q9: Which of the following would BEST describe
Q10: Rich is a manager in the accounting
Q13: Which of the following methodologies might be
Q41: Which of the following methodologies might be
Q47: Which of the following methodologies might be
Q72: The most common reason for schedule and
Q74: Which of the following methodologies is the