Which Is NOT Part of the Requirements Gathering Process

Question 79

Multiple Choice

Which is NOT part of the requirements gathering process?


A) Is used for building political support for the project
B) Is used for establishing trust and rapport between the project team and users
C) Determining 'if we build it, they will come'
D) Key stakeholders need to be included
E) Involving people who may feel slighted if their input is not considered

Correct Answer:

verifed

Verified