Multiple Choice
If a program does not pass a test:
A) The analyst will verify that the use-cases were correctly formulated
B) The program is sent back to the development team
C) The project manager will verify that the test was or was not appropriate for the code being tested
D) The project will be scratched
E) More programming staff will be added to the project f) The testing methods and test data will be changed
Correct Answer:

Verified
Correct Answer:
Verified
Q13: Bruce is a senior project manager.What activities
Q16: System tests are usually conducted by:<br>A)Programmers (developers)<br>B)Project
Q19: Christine is a senior user in the
Q20: Integration testing:<br>A)Is to verify that batch processing
Q21: Over the years (as shown by Fredrick
Q26: The normal order for testing is: unit
Q27: Frequently a project manager will create a
Q31: When developing navigational controls for online documentation,you
Q33: As compared to integration testing,system testing:<br>A)Is much
Q49: Myles is a systems analyst on a