    If a Trainer Has Been Hired to Train All Staff
Solved

If a Trainer Has Been Hired to Train All Staff

Question 20

Question 20

Multiple Choice

If a trainer has been hired to train all staff before the new system goes 'live',it might be best to use:


A) direct conversion
B) pilot conversion
C) phased conversion
D) modular conversion
E) perpendicular conversion

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15: The biggest problem with parallel conversion is

Q16: Technical readiness in a migration plan is

Q18: The authors suggest that computer based training

Q19: Training should focus on how to use

Q23: According to the quote from Machiavelli The

Q24: A 'technology restructuring matrix' describes how to

Q25: There are two 'conversion module' options.What are

Q34: How can careful training help adoption of

Q57: Frequently,as people get used to certain ways

Q65: Research has shown that about _ of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines