Multiple Choice
When considering costs of a new system conversion,which is NOT a common cost to consider?
A) the cost of running two systems with a parallel conversion
B) the costs of more staff at more locations for support in a simultaneous conversion
C) the salary costs of users,trainers,administrators,consultants
D) the hardware costs for a pilot system
E) the extra programming costs for a modular conversion
Correct Answer: