Multiple Choice
Given the order-requirement digraph for a collection of tasks shown below, what would the critical path be?
A) T1, T2, T3
B) T4, T2, T3
C) T4, T3
D) T4, T5, T6
Correct Answer:

Verified
Correct Answer:
Verified