Use the order-requirement digraph below (with time given in minutes) and the priority list T1, T2, T 3, T4, T5, T6 to answer Questions 13-16. Use the order-requirement digraph below (with time given in minutes) and the priority list T<sub>1</sub>, T<sub>2</sub>, T <sub>3</sub>, T<sub>4</sub>, T<sub>5</sub>, T<sub>6</sub> to answer Questions 13-16.   -Apply the list-processing algorithm to construct a schedule using two processors.
-Apply the list-processing algorithm to construct a schedule using two processors.