Given the Order-Requirement Digraph Below (With Time Given in Minutes)

Question 12

Multiple Choice

Given the order-requirement digraph below (with time given in minutes) and the priority list T1, T4, T 5, T2, T3, T6, apply the list-processing algorithm to construct a schedule using two processors. How much time does the resulting schedule require? Given the order-requirement digraph below (with time given in minutes)  and the priority list T<sub>1</sub>, T<sub>4</sub>, T <sub>5</sub>, T<sub>2</sub>, T<sub>3</sub>, T<sub>6</sub>, apply the list-processing algorithm to construct a schedule using two processors. How much time does the resulting schedule require?   A)  21 minutes B)  22 minutes C)  23 minutes D)  24 minutes


A) 21 minutes
B) 22 minutes
C) 23 minutes
D) 24 minutes

Correct Answer:

verifed

Verified