Solved

Given the Order-Requirement Digraph Below (With Time Given in Minutes)

Question 29

Multiple Choice

Given the order-requirement digraph below (with time given in minutes) , apply the critical-path scheduling algorithm to construct a schedule using two processors. How much time does the resulting schedule require? Given the order-requirement digraph below (with time given in minutes) , apply the critical-path scheduling algorithm to construct a schedule using two processors. How much time does the resulting schedule require?   A)  21 minutes B)  22 minutes C)  23 minutes D)  24 minutes


A) 21 minutes
B) 22 minutes
C) 23 minutes
D) 24 minutes