Solved

Use the Decreasing-Time-List Algorithm to Schedule These Tasks on Two 9 minutes, 2 minutes, 8 minutes, 5 minutes, 4 minutes, 8 minutes 9 \text { minutes, } 2 \text { minutes, } 8 \text { minutes, } 5 \text { minutes, } 4 \text { minutes, } 8 \text { minutes }

Question 3

Multiple Choice

Use the decreasing-time-list algorithm to schedule these tasks on two machines: How much time does the resulting schedule require? 9 minutes, 2 minutes, 8 minutes, 5 minutes, 4 minutes, 8 minutes 9 \text { minutes, } 2 \text { minutes, } 8 \text { minutes, } 5 \text { minutes, } 4 \text { minutes, } 8 \text { minutes }


A) 17 minutes
B) 18 minutes
C) 19 minutes
D) 22 minutes

Correct Answer:

verifed

Verified