Exhibit 14.13
The following questions use the information below.
A student wants to buy a new car. She has three cars to choose from, A, B and C. The cars differ with respect to price, performance and looks. The student has developed the following AHP tables for price and summary. The other tables are not shown due to space limitations.
-The main difference between CPM and PERT is that
A) CPM is deterministic and PERT is probabilistic
B) CPM is probabilisttic and PERT is deterministic
C) CPM is best for longer projects while PERT is best for shorter projects
D) CPM requires 3 duration estimates for each activity while PERT requires only one duration estimate for each activity
Correct Answer:

Verified
Correct Answer:
Verified
Q69: Exhibit 15.2<br>The following questions employ the AON
Q70: Exhibit 14.13<br>The following questions use the information
Q71: Exhibit 15.1<br>The following questions employ the AON
Q72: If we are employing Activity-On-Arc (AOA) network
Q73: Exhibit 14.13<br>The following questions use the information
Q75: Exhibit 15.3<br>The following questions are based on
Q76: Exhibit 14.13<br>The following questions use the information
Q77: Exhibit 14.13<br>The following questions use the information
Q78: Exhibit 14.13<br>The following questions use the information
Q79: Exhibit 15.2<br>The following questions employ the AON