Multiple Choice
Exhibit 15.2
The following questions employ the AON network and completed spreadsheet below.
-What is the formula for the earliest finish time for activity i?
A) EFTi = ESTi + ti
B) EFTi = EFTj + tj
C) EFTi = EFTi−1 + ti
D) EFTi = ESTi − ti
Correct Answer:

Verified
Correct Answer:
Verified