Multiple Choice
Exhibit 15.1
The following questions employ the AON network and partial spreadsheet below.
-What is the latest finish time for activity D in the following diagram?
A) 6
B) 13
C) 14
D) 15
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Exhibit 15.2<br>The following questions employ the AON
Q56: Exhibit 15.1<br>The following questions employ the AON
Q57: Exhibit 15.4<br>The following questions are based on
Q58: Exhibit 15.2<br>The following questions employ the AON
Q59: How many paths are there in the
Q61: Exhibit 15.1<br>The following questions employ the AON
Q62: Exhibit 14.13<br>The following questions use the information
Q63: Exhibit 15.5<br>The following questions use the information
Q64: The critical path is the _ path
Q65: Exhibit 15.6<br>The following questions use the information