Multiple Choice
Odonell Corporation estimates that its variable manufacturing overhead is $11.20 per machine-hour and its fixed manufacturing overhead is $563,640 per period.
-If the denominator level of activity is 1,100 machine-hours, the predetermined overhead rate would be:
A) $960.00 per machine-hour
B) $9.60 per machine-hour
C) $13.30 per machine-hour
D) $22.90 per machine-hour
Correct Answer:

Verified
Correct Answer:
Verified