Zike Corporation's static planning budget for October appears below. The company bases its budgets on machine-hours.
In October, the actual number of machine-hours was 6,000, the actual supplies cost was $14,740, the actual power cost was $49,170, the actual salaries cost was $15,390, and the actual equipment depreciation was $63,670.
-The spending variance for power cost in the flexible budget performance report for the month should be:
A) $3,570 U
B) $1,170 U
C) $3,570 F
D) $1,170 F
Correct Answer:

Verified
Correct Answer:
Verified
Q54: Gearhart Corporation bases its budgets on the
Q55: Zelenka Clinic uses client-visits as its measure
Q56: A flexible budget report should contain variable
Q57: Nicolaysen Corporation manufactures and sells a single
Q58: Thune Memorial Diner is a charity supported
Q60: Towne Snow Removal's cost formula for its
Q61: Buonocore Clinic uses client-visits as its measure
Q62: Linscott Corporation manufactures and sells a single
Q63: Drey Jeep Tours operates jeep tours in
Q64: Larance Detailing's cost formula for its materials