If the project leader now believes that C should be 6 (not 4) ,the critical path is now:


A) EG
B) ACH
C) BFI
D) ABC
E) none of these

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q4: Systems survey work include gathering data on

Q20: An advantage of prototyping is that models

Q39: A disadvantage of outsourcing is that a

Q51: The information needs of top managers tend

Q59: The most important factor in planning for

Q72: An important first step in the systems

Q92: A student fails a course at his

Q97: For a system to be totally feasible,

Q107: The search for more efficient ways to

Q108: Which one of these design feasibility areas

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines