In a minimum cost network flow model,the flow balance constraint for each demand node takes the form
A) Flow out Flow in + Net supply
B) Flow in Flow out + Net demand
C) Flow in = Flow out
D) Flow in Flow out + Net demand
E) Flow out Flow in + Net demand
Correct Answer:

Verified
Correct Answer:
Verified