Multiple Choice
Bok Company's output for the current period was assigned a $200,000 standard direct materials cost. The direct materials variances included a $5,000 favorable price variance and a $3,000 unfavorable quantity variance. What is the actual total direct materials cost for the current period?
A) $208,000.
B) $198,000.
C) $202,000.
D) $192,000.
E) $205,000.