Multiple Choice
Bok Company's output for the current period was assigned a $400,000 standard direct labor cost. The direct labor variances included a $10,000 unfavorable direct labor rate variance and a $4,000 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?
A) $414,000.
B) $386,000.
C) $394,000.
D) $406,000.
E) $410,000.
Correct Answer:

Verified
Correct Answer:
Verified
Q45: A company uses the following standard costs
Q47: Perkins Company provides the following data developed
Q48: Standard costs are:<br>A) Actual costs incurred to
Q51: Identify the situation that will result in
Q54: A flexible budget performance report compares the
Q100: When the actual cost of direct materials
Q144: Differences between actual costs and standard costs
Q150: The difference between the flexible budget sales
Q201: Identify and explain the primary differences between
Q202: _ are preset costs for delivering a