Multiple Choice
Which of the following should not be included in a schedule of cash flows from operations when evaluating a capital project?
A) Fixed costs.
B) Sunk costs.
C) Depreciation and amortization.
D) Variable costs.
Correct Answer:

Verified
Correct Answer:
Verified